How to Do Blockwork Marking: Essential Guide

What is Blockwork Marking ?

Blockwork marking is the process of transferring the wall layout from the approved drawings onto the actual floor/slab at site before starting block masonry work.

In simple terms:

Block work marking tells the mason exactly where the block wall has to be constructed.

blockwork marking

Tools and Equipments used for Blockwork Marking:

Tool / EquipmentPurpose
Measuring tapeChecking wall lengths, offsets, openings and dimensions
Chalk line / snap lineMarking straight wall lines on the slab
Chalk powder / marking powderCreating visible reference lines
Marker / paint markerIdentifying wall lines, openings and reference points
Steel scaleChecking small dimensions and offsets
Try squareChecking 90° corners and small layouts
Spirit levelChecking local horizontal/vertical alignment
Laser distance meterQuick and accurate distance measurements
Laser levelTransferring horizontal levels and reference lines
Auto levelEstablishing and checking required elevations
Total stationAccurate setting-out of coordinates, gridlines and wall locations
Plumb bobTransferring vertical reference points where required
String lineMaintaining straight reference/alignment lines
Wooden/metal pegs or pinsEstablishing temporary reference points
HammerFixing pins/pegs where required
PPESafety during marking and site activities

Procedure for Blockwork Marking :

  • Transfer the 1m Mark to all the columns along which block masonry has to be done
  • An Aluminum Straight edge of length not less than 2m is marked at every at 200mm(190mmblock thickness + 10mm mortar thickness), Starting from one edge, up to 2m.
blockwork marking
  • Wherever block work has to be done, the mark on the straight edge corresponding to a height of 1m from the bottom is coincided with the 1m mark, which has been transferred onto the columns.
  • Tie the String line from the column to column at whichever course that has to be constructed along alignment of the wall as per drawing.
  • This will ensure perfect horizontally of each course of block masonry and also control the mortar joint thickness.
  • Ensure that the locations of openings like windows, doors and ventilators are known.
  • In between the sill level and the bottom of the beam has to be measured.
  • Calculate the number of full blocks and the mortar joints that can be accommodated within this height (as the mortar joint thickness and the block height is known).
  • There is a possibility of a gap occurring between the beam bottom and the topmost full block courses tht can be constructed.
  • The height of this gap (adjuster coarse height) is marked at the lintel level or Above the sill level. Further marking is continued as before up to the beam
  • It is preferrable to start a marking coarse from the peripheral walls and then continue marking the inner walls an of Apartments.

Inspection Method for Blockwork Marking :

Visual Inspection

Check:

  • Visibility of marking
  • Continuity of lines
  • Wall intersections
  • Reference points
  • Opening locations
  • Clarity of identification

Tape Measurement

Use a calibrated measuring tape to verify:

  • Wall length
  • Opening width
  • Opening location
  • Offsets
  • Wall thickness

Measurements should be taken from established reference points rather than from random nearby walls.

Laser Level

A laser level can be used to transfer or verify:

  • Horizontal reference
  • Wall alignment
  • Level references
  • Opening levels

Auto Level

An auto level may be used where accurate elevation transfer is required.

Typical applications include:

  • Sill level
  • Lintel level
  • Floor reference
  • 1 m level
  • Other specified elevations

Total Station

For large buildings or projects requiring higher setting-out control, a total station may be used to establish:

  • Gridlines
  • Wall coordinates
  • Column references
  • Major offsets
  • Building control points

Cross-Check With Drawings

Finally, compare the physical marking with the latest approved drawing.

This is one of the most important steps.

A dimension may be physically measured correctly but still be wrong if the wrong drawing revision was used.


FAQS :


Internal references:

  1. How to Do Slab Level Marking: Essential Construction QA/QC Guide
  2. How to Mark PCC, Footings & Starter Columns | Complete Guide
  3. Ultimate Surveying Instruments for Precise Setting Out